Click here to watch a video on the Tasiast Mill Re-start as of November 10, 2021.
Since the Tasiast mill fire in June 2021, excellent progress has been made re-starting milling operations. The mill has re-started at costs lower than original estimates. The mill is now ramping up and is expected to produce approximately 15,000 Au eq. oz. during Q4 2021. Tasiast remains on schedule to reach throughput of 21,000 tonnes per day by the end of Q1 2022.
For more information, view our third-quarter news release here.