Video: Update on Round Mountain Phase W expansion project

The Round Mountain Phase W expansion project continues to make strong progress, with major project elements complete or nearing completion, and commissioning of the processing circuit has now commenced, ahead of schedule.

The Phase W expansion includes a layback of the existing pit, a new heap leach pad and vertical carbon-in-column plant, relocation of some existing infrastructure, and additions to the mining fleet.

Phase W ore is now being placed on the new heap leach pad, which was completed in Q1 2019. It is 9 million square feet large, designed for 65 million tons of ore stacked up to a height of 250 feet.

See how the expansion is progressing here.

In September 2017, Kinross announced it would be proceeding with the Phase W expansion. It is expected to add approximately 1.5 million gold ounces to the life of mine and extend mining by five years at one of our most consistent operations, located in one of the best mining jurisdictions in the world. 

Analysts tour Tasiast and learn more about the operation
December 6, 2023

Analysts tour Tasiast and learn more about the operation

Kinross breaks ground on Manh Choh project in Alaska!  
October 17, 2023

Kinross breaks ground on Manh Choh project in Alaska!  

Kinross Tasiast successfully ‘takes off’ with Skycatch survey drone solution!
September 19, 2023

Kinross Tasiast successfully ‘takes off’ with Skycatch survey drone solution!